Mock Up Wall



 I will be adding to this post as progress continues.  Edile is required to build a "mock up" wall to show their ability to build the temple.  They are doing the same thing they would do on the temple and using the exact same materials.  It is to show they are able to do it. This will eventually be torn down.

Here are the columns that would be placed over pilings if they needed them here.

Here is a wall made of cinder block, which is what the walls will be on the temple.  They had the first layer laid and were working on the second and they didn't stagger the blocks so the joints matched up.  They had to tear it down and Cory, Leslie, and Blaise taught them how it needed to be done and they rebuilt. The gap in the center is where they will be putting in a window. 